Milestone N. | Milestone name | WP | Lead beneficiary | Delivery date | Comments |
---|---|---|---|---|---|
MS9 | User prototype archive review | WP2, WP3 | UEDIN | 01/10/2015 | being delayed by 3 to 6 months in order to synchronise with the DPAC CU9 Gaia DR1 rehearsal and beta–testing of GACS. |
MS16 | GENIUS products availability | WP1, WP2, WP3, WP4, WP5, WP6, WP7 | UB | 01/04/2017 | GENIUS products availability |
MS17 | Handover of GENIUS portal to Gaia community | WP7 | CSUC | 01/04/2017 | Handover of GENIUS portal to Gaia community |
MS14 | Load of actual Gaia data | WP3, WP5 | CNRS | 01/01/2017 | Load of actual Gaia data |
MS1 | Kick-off meeting (plenary) | WP1 | UB | 01/11/2013 | Meeting took place 4-5 Dec 2013 |
MS3 | Hiring of main developers | WP1, WP2, WP3, WP5, WP4, WP6, WP7 | UB | 01/06/2014 | |
MS5 | Archive user requirements document | WP2 | UL | 01/10/2014 | |
MS10 | Exploitation tools review | WP2, WP4 | UB | 01/10/2015 | |
MS13 | Stress test | WP3 | UEDIN | 01/09/2016 | |
MS15 | Completion meeting & final external review | WP1 | UB | 01/03/2017 | |
MS8 | Mid-term review | WP1, WP2, WP3, WP4, WP5, WP6, WP7 | UB | 01/06/2015 | Plenary meeting to take place in Sept in Barcelona. Mid term review in Nov. 2015 in Leiden (agreed with PO during the 1st year review) |
MS7 | Public version of GENIUS portal | WP6, WP7 | CSUC | 01/10/2014 | Public version of GENIUS portal |
MS2 | Agreed testbed environment with ESAC-SAT & CU9 | WP3 | UEDIN | 01/02/2014 | The testbed for Archive development has been agreed with SAT. And is based on the Gaia Archive Core System (GACS) described at the CU9 SDP.. |
MS4 | GENIUS portal available at CESCA for internal use | WP6, WP7 | CSUC | 01/04/2014 | Two GENIUS portal developed at CESCA: one dedicated to the project and one for more general dissemination. |
MS12 | Prototype archive tools open to community | WP1, WP2, WP3, WP4, WP5, WP6, WP7 | UB | 01/10/2015 | User testing will allow to give the necessary feedback on the archive tools which have been developed. Most Gaia data will not be available at the date of the milestone, but the testing will nevertheless be possible by providing access to simulated data. In order to get a feedback as large as possible on the archive tools, the access will be given to a large panel of users within and outside the Gaia community. They will e.g. be selected among the users having made requirements proposals (cf. GAIA-C9-TN-LEI-AB-026-1). |
MS11 | Validation tools review | WP2, WP5 | CNRS | 01/10/2015 | Validation tools review |
MS6 | Requirements document for each subsystem | WP2, WP3, WP4, WP5 | UB | 01/10/2014 | WP3 SRS |