Milestone N. | Milestone name | WP | Lead beneficiary | Delivery date | Comments |
---|---|---|---|---|---|
MS2 | Agreed testbed environment with ESAC-SAT & CU9 | WP3 | UEDIN | 01/02/2014 | The testbed for Archive development has been agreed with SAT. And is based on the Gaia Archive Core System (GACS) described at the CU9 SDP.. |
MS5 | Archive user requirements document | WP2 | UL | 01/10/2014 | |
MS15 | Completion meeting & final external review | WP1 | UB | 01/03/2017 | |
MS10 | Exploitation tools review | WP2, WP4 | UB | 01/10/2015 | |
MS4 | GENIUS portal available at CESCA for internal use | WP6, WP7 | CSUC | 01/04/2014 | Two GENIUS portal developed at CESCA: one dedicated to the project and one for more general dissemination. |
MS16 | GENIUS products availability | WP1, WP2, WP3, WP4, WP5, WP6, WP7 | UB | 01/04/2017 | GENIUS products availability |
MS17 | Handover of GENIUS portal to Gaia community | WP7 | CSUC | 01/04/2017 | Handover of GENIUS portal to Gaia community |
MS3 | Hiring of main developers | WP1, WP2, WP3, WP5, WP4, WP6, WP7 | UB | 01/06/2014 | |
MS1 | Kick-off meeting (plenary) | WP1 | UB | 01/11/2013 | Meeting took place 4-5 Dec 2013 |
MS14 | Load of actual Gaia data | WP3, WP5 | CNRS | 01/01/2017 | Load of actual Gaia data |
MS8 | Mid-term review | WP1, WP2, WP3, WP4, WP5, WP6, WP7 | UB | 01/06/2015 | Plenary meeting to take place in Sept in Barcelona. Mid term review in Nov. 2015 in Leiden (agreed with PO during the 1st year review) |
MS12 | Prototype archive tools open to community | WP1, WP2, WP3, WP4, WP5, WP6, WP7 | UB | 01/10/2015 | User testing will allow to give the necessary feedback on the archive tools which have been developed. Most Gaia data will not be available at the date of the milestone, but the testing will nevertheless be possible by providing access to simulated data. In order to get a feedback as large as possible on the archive tools, the access will be given to a large panel of users within and outside the Gaia community. They will e.g. be selected among the users having made requirements proposals (cf. GAIA-C9-TN-LEI-AB-026-1). |
MS7 | Public version of GENIUS portal | WP6, WP7 | CSUC | 01/10/2014 | Public version of GENIUS portal |
MS6 | Requirements document for each subsystem | WP2, WP3, WP4, WP5 | UB | 01/10/2014 | WP3 SRS |
MS13 | Stress test | WP3 | UEDIN | 01/09/2016 | |
MS9 | User prototype archive review | WP2, WP3 | UEDIN | 01/10/2015 | being delayed by 3 to 6 months in order to synchronise with the DPAC CU9 Gaia DR1 rehearsal and beta–testing of GACS. |
MS11 | Validation tools review | WP2, WP5 | CNRS | 01/10/2015 | Validation tools review |