GENIUS Milestones |
|
MS6 |
Requirements document for each subsystem |
WP2, WP3, WP4, WP5 |
UB |
01/10/2014 |
WP3 SRS |
MS7 |
Public version of GENIUS portal |
WP6, WP7 |
CSUC |
01/10/2014 |
Public version of GENIUS portal |
MS8 |
Mid-term review |
WP1, WP2, WP3, WP4, WP5, WP6, WP7 |
UB |
01/06/2015 |
Plenary meeting to take place in Sept in Barcelona. Mid term review in Nov. 2015 in Leiden (agreed with PO during the 1st year review) |
|
|
< < |
MS9 |
User prototype archive review |
WP2, WP3 |
UEDIN |
01/10/2015 |
being delayed by 3 to 6 months in order to synchronise with the DPAC CU9 Gaia DR1 rehearsal and beta–testing of GACS. |
|
> > |
MS9 |
User prototype archive review |
WP2, WP3 |
UEDIN |
01/10/2015 |
Completed (with delay, as described in the previous report) by the beta-testing group of the Gaia archive. |
|
|
|
|
< < |
MS12 |
Prototype archive tools open to community |
WP1, WP2, WP3, WP4, WP5, WP6, WP7 |
UB |
01/10/2015 |
User testing will allow to give the necessary feedback on the archive tools which have been developed. Most Gaia data will not be available at the date of the milestone, but the testing will nevertheless be possible by providing access to simulated data. In order to get a feedback as large as possible on the archive tools, the access will be given to a large panel of users within and outside the Gaia community. They will e.g. be selected among the users having made requirements proposals (cf. GAIA-C9-TN-LEI-AB-026-1). |
|
> > |
MS12 |
Prototype archive tools open to community |
WP1, WP2, WP3, WP4, WP5, WP6, WP7 |
UB |
01/10/2015 |
User testing will allow to give the necessary feedback on the archive tools which have been developed. Most Gaia data will not be available at the date of the milestone, but the testing will nevertheless be possible by providing access to simulated data. In order to get a feedback as large as possible on the archive tools, the access will be given to a large panel of users within and outside the Gaia community. They will e.g. be selected among the users having made requirements proposals (cf. GAIA-C9-TN-LEI-AB-026-1). |
|
|
MS13 |
Stress test |
WP3 |
UEDIN |
01/09/2016 |
|
MS14 |
Load of actual Gaia data |
WP3, WP5 |
CNRS |
01/01/2017 |
Load of actual Gaia data |
MS15 |
Completion meeting & final external review |
WP1 |
UB |
01/03/2017 |
|
|