Milestone N. |
Milestone name |
WP |
Lead beneficiary |
Delivery date |
Comments |
MS1 |
Kick-off meeting (plenary) |
WP1 |
UB |
01/11/2013 |
Meeting took place 4-5 Dec 2013 |
MS2 |
Agreed testbed environment with ESAC-SAT & CU9 |
WP3 |
UEDIN |
01/02/2014 |
The Gaia CU9 SDP has been adopted as the document to follow. |
MS3 |
Hiring of main developers |
WP1, WP2, WP3, WP4, WP5, WP6, WP7 |
UB |
01/02/2014 |
|
MS4 |
GENIUS portal available at CESCA for internal use |
WP6, WP7 |
CESCA |
01/04/2014 |
GENIUS portal available at CESCA for internal use |
MS5 |
Archive user requirements document |
WP2 |
UL |
01/10/2014 |
|
MS6 |
Requirements document for each subsystem |
WP2, WP3, WP4, WP5 |
UB |
01/10/2014 |
|
MS7 |
Public version of GENIUS portal |
WP6, WP7 |
CESCA |
01/10/2014 |
Public version of GENIUS portal |
MS8 |
Mid-term review |
WP1, WP2, WP3, WP4, WP5, WP6, WP7 |
UB |
01/06/2015 |
|
MS9 |
User prototype archive review |
WP2, WP3 |
UEDIN |
01/10/2015 |
|
MS10 |
Exploitation tools review |
WP2, WP4 |
UB |
01/10/2015 |
|
MS11 |
Validation tools review |
WP2, WP5 |
CNRS |
01/10/2015 |
Validation tools review |
MS12 |
Prototype archive tools open to community |
WP1, WP2, WP3, WP4, WP5, WP6, WP7 |
UB |
01/10/2015 |
User testing will allow to give the necessary feedback on the archive tools which have been developed. Most Gaia data will not be available at the date of the milestone, but the testing will nevertheless be possible by providing access to simulated data. In order to get a feedback as large as possible on the archive tools, the access will be given to a large panel of users within and outside the Gaia community. They will e.g. be selected among the users having made requirements proposals (cf. GAIA-C9-TN-LEI-AB-026-1). |
MS13 |
Stress test |
WP3 |
UEDIN |
01/09/2016 |
|
MS14 |
Load of actual Gaia data |
WP3, WP5 |
CNRS |
01/01/2017 |
Load of actual Gaia data |
MS15 |
Completion meeting & final external review |
WP1 |
UB |
01/03/2017 |
|
MS16 |
GENIUS products availability |
WP1, WP2, WP3, WP4, WP5, WP6, WP7 |
UB |
01/04/2017 |
GENIUS products availability |
MS17 |
Handover of GENIUS portal to Gaia community |
WP7 |
CESCA |
01/04/2017 |
Handover of GENIUS portal to Gaia community |